Sbc for design work of construction. Methodological instructions for the use of reference books of base prices for design work

STATENEW COMMITTEE OF THE RO SSSIAN FEDERATION FOR
CONSTRUCTION AND HOUSING MMU ON THE LINEN COMPLEX

GOSSTROY RUSSIA

GENERAL INSTRUCTIONS
ON APPLICATION OF REFERENCES OF BASIC PRICES
FOR DESIGN WORKS FOR CONSTRUCTION

Approved
Go's ruling
with from Russia from 07.08.02 No. 102

MOSCOW2002

General guidelines for the use of Reference Price Guides for design work for construction have been developed by the Federal State InstitutionNS" CENTRINVESTproject» Gosstroy of Russia.

Submitted and prepared for approval by the Office of Pricing and Estimated Rationing in Construction and the Housing and Utilities Complex of the Gosstroy of Russia.

Commissioned since 10August 2002 by the decree of the Gosstroy of Russia from 07. 08. 02 № 102.

INTRODUCTION

Reference books of base prices for design work for construction (hereinafter referred to as Reference books) are intended to determine base prices for the subsequent formation of contract prices for the development of design documentation for new construction, expansion, reconstruction and technical re-equipment of production and f or some railway Anskoy destination.

General instructions are obligatory for use when using the prices for design work, given in all References.

I. GENERAL INSTRUCTIONS FOR THE APPLICATION OF REFERENCES OF BASIC PRICES FOR DESIGN WORKS FOR CONSTRUCTION

1... Reference books are s started to be used by organizations of various organizational and legal forms, which, according to the legislation of the Russian Federation, have the status of a legal entity.

2... Base prices in the Reference Books are set depending on the natural indicators of the design objects (capacity, length, capacity, area, etc.) and on the total cost of construction.

3... The prices given in the Directories are set in accordance with the composition, procedure for the development, coordination and approval of project documentation for the construction of enterprises, buildings, structures provided for.

4... The Directories show prices for individual design of new construction of facilities, buildings and structures, as well as individual elements of the complex using materials from standard and reusable economical individual projects of workshops, buildings and structures that are part of them, as well as drawings of typical building structures, products and nodes.

5... Prices in the Directories are set as of January 1, 2001

Prices include all costs for the development of project documentation and profit, excluding value added tax.

6... The following works and services are taken into account by the prices of the Directories and do not require additional payment:

6. 1production of demonstration materials (except for demonstration models);

6. 2participation of the design organization together with the customer in the approval of the finished design documentation with state bodies and local self-government bodies;

6. 3defense of a working draft (project) for expert examination yu and approving instances.

7... The complex prices of the Directories for the development of project documentation do not include the costs of:

7. 1development of design solutions specified in the design assignment in several versions, with the exception of variant studies for the selection of optimal design solutions.

The development of additional options for the project, working project or individual technological, structural, architectural and other solutions is established in the design assignment, where sections (or parts of these sections) of the project must also be defined, according to which the development of these options and the initial data necessary for them must be determined. development.

The degree of elaboration of additional options is established by agreement with the customer.

In the development process, both the main and additional options, a variant study of design solutions is carried out;

7. 2development of working drawings for special auxiliary structures, devices, devices and installations in the design of objects with particularly complex structures and work methods.

The base price for the development of working drawings of these structures, fixtures and fittings is determined in the manner prescribed by construction organizations, or by calculating the cost in accordance with the cost estimate;

7. 3development of solutions for the monumental and decorative design of enterprises, buildings and structures.

Such work, in cases where it is provided for by the design assignment, is performed, as a rule, by organizations of the art fund under separate contracts and prices;

7. 4making changes to the design documentation (with the exception of correcting errors made by the design organization).

The performance of these works should be provided for by an assignment for the design of an object or by a separate order of the customer and paid additionally;

7. 5development of details lyric x drawings of metal structures (KMD) and factory-made process pipelines.

The costs of the design organization performing the development of structural steel drawings on behalf of the customer are determined according to departmental prices of manufacturers or on the basis of cost estimates and are paid additionally;

7. 6surveys and measurement work at facilities subject to reconstruction, expansion and technical re-equipment.

The cost of such work should be determined according to the relevant Reference books, or by calculating the cost in accordance with the cost estimate;

7. 7development of design documentation for custom-made equipment, except for the preparation of initial requirements for the design of this equipment.

The reference book of basic prices takes into account the costs of drawing up the initial requirements for the development of design documentation for custom-made equipment, including single and small-scale ones. The terms of reference for the specified equipment are developed by the manufacturer.

In some cases, when the development of the specified design documentation is entrusted to the design organization, it is carried out, as a rule, under contracts with the equipment manufacturer. If the manufacturer is not determined, then the development of design documentation for the equipment can be carried out by the design organization on behalf of the customer. In this case, the base price for the performance of the specified design work is determined according to the departmental prices of the manufacturers of the specified equipment;

7. 8business trips.

The basic prices of the Directory do not take into account the costs of business trips, including the costs of administrative personnel, if the travel of these personnel is directly related to the design of the facility;

7. 9development of projects for the production of construction and installation works (P ETC);

7.10development of design documentation for the construction of temporary buildings and structures for the needs of construction organizations;

7.12research and experimental work;

7.13development of automated enterprise management systems(AS UP ) and automated process control systems (APCS).

The base price for the design of ACS and ACS is determined according to the corresponding price documents for the development of the specified technical documentation;

7. 14development of the ITM GOChS section;the base development price is determined according to the relevant Reference Book;

7.15development of an EIA section;

7. 16development of interiors performed in accordance with.

II. PROCEDURE FOR DETERMINING BASIC PRICES FOR DESIGN WORKS

A. Depending on the natural indicators of the design objects

1... The base price for the development of project documentation (project + working documentation) is determined by the formula:

C =(a + inx) × TOi,

where

"but"and "in" - constant values ​​for a certain interval of the main indicator of the projected object, in thousand rubles.;

NS -the main indicator of the projected object;

TOi -

2... The prices of References for the development of design documentation for enterprises, workshops, buildings and structures take into account the cost of designing all internal morningsite x engineering networks, communications, structures and devices (power supply, water supply, sewerage, heat supply, etc.), including the connection of workshops, buildings and structures to them, as well as the master plan and improvement within the construction site. If the price in the Directory is set for the development of design documentation for the main production (excluding auxiliary, as well as site engineering networks and structures), a comprehensive assessment is carried out by a set of cost indicators for the design of main and auxiliary facilities.

Offsite design priceNS x engineering networks and communications by complex prices are not taken into account and is determined additionally.

3... The price for the development of design documentation for individual workshops, buildings and structures, carried out by subcontracted design organizations, in cases where the cost of designing these objects is taken into account by the prices of the relevant Directory, is determined at the same prices at which the cost of design was determined by the general designer.

4... If the projected object has a value of the main indicator less than the minimum or more than the maximum indicators given in the tables of prices in the Directories, the price for the development of project documentation is determined by extrapolation in accordance with the formula given in the appendix.

In cases where the adopted indicator is less than half of the minimum or more than twice the maximum indicator given in the table, the base price of design work is determined in the manner prescribed by clause.

7... The price for the development of technical documentation for the overhaul of building structures of buildings and structures is determined according to the relevant Reference Price Reference.

If it is impossible to apply the specified Guide, the price of work can be determined using the corresponding References of basic prices for design work for the conditions of new construction with the application of a reduction factor to the design price for the conditions of new construction in the amount of not more than 0, 5depending on the scope of work.

8... The costs of design organizations located in areas in which, in accordance with the current legislation, payments are made due to regional regulation of wages, incl. payments according to regional coefficients, as well as wage increments for continuous work experience and other benefits provided for by legislation in the regions of the Far North and equivalent areas, are determined additionally by introducing increasing coefficients to the total base price established on the basis of the relevant justifying calculations performed by the design organization itself.

The method for calculating the multiplying coefficients is set out in the "Recommendations for determining the coefficient to the base prices for design work, taking into account the additional costs of organizations for preferential salary payments", approved and recommended for use by the letter of the State Construction Committee of Russia dated 30... 06. 98, No. 9-10-17 / 40.

B. From the generalth construction costs

9... The base price of design documentation (project + working documentation) is determined from the total cost of construction, depending on the complexity categories of design objects.

10... The price of design documentation includes the cost of designing the entire complex of buildings, structures and types of design work, which are reflected in the total cost of construction, determined by an analogue object, taking into account their comparability or by aggregated indicators of estimated standards (per unit of indicators:1sq. m total area, 1 cub. mvolume of the building, 1 NS. m tracks, 1 hadevelopment, per unit of capacity, productivity, etc.).

11.Determination of the price of design documentation is carried out according to tables corresponding to the purpose of design objects.

12... The base price of project documentation is determined by the formula:

C = C 01 × K i ,

where

WITH -base price of project documentation at current prices;

C 01 - base price of design documentation for 01... 01.2001;

TO i - coefficient reflecting inflationary processes at the time of determining the price of design work for the construction of the facility.

To recalculate the cost of construction of objects from the price level as of 01. 01. 2000at the price level as of 01. 01. 2001g. a coefficient equal to1, 38.

13... In cases where the projected object has a construction cost value that is between the indicators given in the table, the base price for the development of project documentation is determined by interpolation.

If the cost of building an object is less or more than the extreme cost indicators given in the price table, the base price of design work is taken in the amounts established for the extreme indicators (without extrapolation in the direction of decreasing or increasing).

14... The price for the development of design documentation for the reconstruction and technical re-equipment of existing enterprises, workshops, buildings and structures is determined based on the cost of the reconstruction object,calculated for the conditions of new construction of these facilities using a multiplying coefficient up to 1, 5and a reduction factor that takes into account the scope of reconstruction work established by the design organization in agreement with the customer.

* * *

15... The distribution of the price of design work by design stages is given in the Reference books and can be specified by agreement between the design organization and the customer.

16... The cost of individual sections of the design documentation, taken into account the base prices, for new construction objects is determined according to the tables of relative (approximate) cost given in the Directories and can be specified by the management of the design organization within the total cost for each design stage, both when performing work on its own and when netransfer of part of the work to subcontractor design organizations in agreement with them.

In the same order, the relative cost of other sections of the design work, taken into account by base prices, but not highlighted in the tables of relative cost, can be determined.

The relative cost of the development of sections of design work during the reconstruction and technical re-equipment of existing enterprises, buildings and structures is established by the design organization within a certain total design cost, depending on the complexity of the work performed.

III. PROCEDURE FOR DETERMINING THE COST OF DESIGN WORKS, TAKING INTO ACCOUNT ADDITIONAL FACTORS AFFECTING THE EMPLOYMENT OF DESIGN

1.The price for the development of project documentation using the model design method is determined by the prices of the Directories with the use of increasing factors.

If there are no established increasing coefficients in the Directories, the price for the development of project documentation by this method is determined by applying the coefficients to the base price: at the "project" stage - 1, 05; at the stage of "working draft" and "working documentation" - 1, 1.

2... The price of design work to be carried out in a reduced composition and volume against that provided for by the current regulatory documents (development of additional project options or individual technological, structural, architectural and other solutions developed in accordance with the design assignment) is determined by the prices for the development of design documentation for the corresponding object using a reduction factor, the size of which is set by the contractor in accordance with the complexity of the work as agreed with the customer.

3... During construction in stages, the price for the development of working projects (projects) of enterprises and structures is determined by the prices of the Directories, based on the main indicators of each stage separately. At the same time, up to 20percent of the cost of developing a working project (without working documentation) or a project of all subsequent stages.

4... The price of linking standard projects is determined according to the prices of the Directories using the coefficient 0, 35.

The price of linking standard projects with the introduction of changes in them is determined by the prices of the Directories using a coefficient of up to 0, 7depending on the complexity of the work.

5... Price for the development of design documentation for the construction of facilities classified as unique and experimental in accordance with clause 8.4 “System of regulatory documents in construction. Basic Provisions ", is determined by the prices of the Directories; at the same time, the coefficient is applied to the cost of those types of design work, the development of which becomes more complicated 1, 5.

6... The price for the development of design documentation for the construction of enterprises, buildings and structures in difficult conditions is determined based on the prices of Directories with application to the cost of design work, for the development of which special requirements are established by the relevant regulatory documents, the following coefficients:

Factors complicating design

Odds

Permafrost e, millet daughter e, swelling soils; karst and landslide phenomena; location of the construction site above mine workings, in flooded areas, etc.

1, 15

Seismicity 7 points

1, 15

Seismicity 8 points

1, 20

Seismicity 9 points

1, 30

If there are two or more complicating factors, coefficients are applied for each factor.

7... The price for the design of enterprises, buildings and structures with the installation of imported main technological equipment used by the design organization for the first time is determined by the prices of the Directories; at the same time, the cost of types of design work, the development of which is complicated due to the use of the specified equipment, as agreed with the customer, is applied a coefficient of up to 1, 3.

8... The costs of design organizations associated with the implementation of the functions of a general designer and supervision of design work transferred to subcontracting are determined in the amount of up to 2% of the price of development of project documentation,transferred to subcontracted design organizations, and are paid additionally.

9... The prices of the Directories include the cost4copies of design documentation issued to the customer.

The cost of copies of design products issued at the request of the customer in excess of the specified quantity is determined in addition to the base price.

10... When determining the cost of design work at the prices of Directories in the presence of several complicating factors and the use of several coefficients in this connection, larger than one, the overall multiplying coefficient is determined by summing their fractional parts and the unit.

When determining the cost of design work using several coefficients, less than one, the overall reduction coefficient is determined by multiplying them.

11... Guidelines for the application of prices and correction factors given in one Handbook are not allowed to be used when determining the cost of design work in accordance with other Directories.

12... When determining the base price of design according to the References of basic prices for design work for construction in the event of a reduction in specific design terms compared to the normative ones, it is recommended to apply the following increasing coefficients in agreement with the customer:

while shortening the term1.2 times before 1, 1;

at 1.4 times - up to 1, 2;

in 2and more times - before 1, 4.

13... The price for the development of project documentation, carried out in accordance with the relevant regulatory documents governing the design of objects for construction abroad, is determined in the following order.

The cost of performing feasibility studies of investments in construction is determined based on prices for project development using a coefficient of 0, 5.

In cases when, when developing justifications, a site (route) is selected for the construction of an enterprise, building, structure, the specified coefficient is increased by 0, 05.

The price for the implementation of projects, working projects and working documentation for the new construction of enterprises, buildings and structures is determined at the prices of the Directories using the corresponding coefficients 1, 2; 1.04 and 1.

The price for the development of design documentation for the reconstruction and technical re-equipment of existing enterprises, buildings and structures is determined in the manner described in paragraphs. and section.

Additionally, coefficients are applied that take into account the influence of complicating factors:

P / p No.

Complicating factors

Development cost coefficients

the project

working documentation, working draft

1.

Translation of text materials of technical documentation, inscriptions on drawings into a foreign language

1, 1

1, 05

2.

Translation of materials of a foreign customer into Russian

1, 03

1, 03

3.

Double check of calculations, drawings and specifications, calculations of the scope of work, estimate documentation and other design materials, making duplicates of cripples, increased requirements for the design and packaging of project documentation

1, 2

1, 1

4.

Other factors affecting the increase in the complexity of design work:

4. 1

Current frequency and voltage, the difference in the permissible limits of fluctuations in the frequency of the current, different from the Russian Federation (to the cost of designing electrical equipment, power supply, weak currents, instrumentation and A, and, if necessary, other sections)

1, 1

1, 05

4. 2

Dry or humid tropical climate

1, 15

1, 1

4. 3

Development of design documentation taking into account the use of equipment and materials by the design organization for the first time, purchased in the customer's countries or supplied from third countries

1, 3

1, 3

4. 4

Application of foreign norms and standards for materials and equipment, performance of structural calculations based on them, etc., agreed by the customer in the design assignment

1, 15

1, 2

4. 5

Additional requirements for design documentation for the construction of facilities on a contract basis, including the preparation of specifications for equipment and materials for temporary import

1, 1

1, 1

Note .

Increasing factors are applied to the cost of sections of the project documentation or their parts, the development of which is more difficult.

Application

Extrapolation and interpolation c iya when calculating the price of design work

In the case when the projected object has a value of the main indicator less than the minimum or more than the maximum indicator given in the table of the Price Book or the Reference Price Guide, the design base price is determined by extrapolation; in this case, the value of the correction to the price decreases by40%, i.e. when calculating the indicator of the designed object NS backsidetaken with the coefficient 0, 6.

If the power indicator of the object is less than the tabular indicator, the base price of its design is determined by the formula:

C = a + b ×(0, 4 × X t iNS + 0.6 × X back ),

where

a, b -constant values ​​taken according to the table of the minimum value of the indicator;

NSTiNS - the minimum indicator given in the table;

X for d -

If the power indicator of the object is greater than the tabular indicator, the base price of its design is determined by the formula:

C = a + b ×(0, 4 × X t ax + 0.6 × X back ),

where

a, b -constant values ​​taken according to the table of the maximum value of the indicator;

NStah -

NS from hell - indicator of the projected object.

In the case when the table contains only the value "but", and the projected object has an indicator value that does not coincide with those given in the table, the base price of its design is determined by interpolation or extrapolation; when extrapolating towards a decrease or increase, the value of the correction to the price decreases by40% (when calculating the value of the correction, a reduction factor is introduced K = 0, 6).

EXAMPLES OF DETERMINING THE BASIC PRICE FOR DESIGNING OBJECTS,

indicators of which are higher, lower or are between the indicators given in the tables of the Handbook *)

*) The indicators of the tables are taken conditionally.

In the Reference Book of Basic Prices for Design Works, a table is given:

P / p No.

Constant values ​​of the base price for the development of project documentation, thousand roubles.

but

in

Sewage sludge incineration facilities, capacity, t NS with . m 3 / year: from 25 to 60

1 t ss. m 3 / year

66, 5

1, 2

In the case when the table shows the values ​​" but " and " in ».

1.It is required to determine the base price for the design of sewage sludge incineration plants with a capacity of 15thousand m 3 / year. The base price is determined by the formula:

WITH= a + b ×(0, 4 × X t iNS + 0.6 × X back ),

where

but and in- constant values ​​taken according to the table of the minimum value of the indicator;

Xm i n - the minimum indicator given in the table;

NSper d - a given indicator of a projected object.

66, 5 + 1, 2 × (0, 4 × 25 + 0, 6 × 15) = 89, 3 tys. rub.

2... It is required to determine the base price for the design of sewage sludge incineration plants with a capacity of 80 tys. m 3 /year. The base price is determined by the formula:

C = a + b ×(0, 4 × X t ax + 0.6 × X back ),

where

butand in- constant values ​​taken according to the table of the maximum value of the indicator;

NStah - the maximum figure given in the table;

X ass -a given indicator of a projected object.

66, 5 + 1.2 × (0.4 × 60 + 0.6 × 80) = 152.9 thousand rubles.

In the Reference Book of Basic Prices for Design Works, a table is given:

P / p No.

Design object name

Unit of measurement of the main indicator of the object

Constant values ​​of the base price for the development of project documentation, thousand rubles

but

in

Flushing water treatment facilities, capacity, m 3 / day.

1 m 3 / day

-

- ”-

40000

-“-

219,4

80000

“-“

369,1

In the case when the table contains only the value " but ».

3... It is required to determine the base price for the design of a wash water treatment plant with a capacity 100 m 3 / s ut.

Calculation example:

44 - ´ (160 - 100) ´ 0, 6 = 4, 3 tys. rub.

4... It is required to determine the base price for the design of a wash water treatment plant with a capacity 300 m 3 / s ut.

The section contains 52 documents:

    Gas equipment and gas supply. Outdoor lighting Reference book of base prices for design work for construction. Gas equipment and gas supply of industrial enterprises, buildings and structures. Outdoor lighting. Gas equipment and gas supply are in operation. Allowance A practical guide to the application of the reference book of base prices for design work for construction. Gas equipment and gas supply of industrial enterprises, buildings and structures. Outdoor lighting. Urban planning documentation is in effect. Manual A manual for determining the construction cost of the development of urban planning documentation. Urban planning documentation is in effect Reference book of base prices for design work for construction. Urban planning documentation. Railways and highways are in operation. Chapter 4., 2nd Edition Reference Book of Base Prices for Design Works for Construction. Railways and highways. Bridges. Tunnels. Subways. Industrial transport. Chapter 4. Artificial structures (2nd edition). Railways and highways are in operation. Manual A manual for determining the relative cost of development of design and estimate documentation (to the Directory of basic prices for design work for construction. Railways and highways. Bridges. Tunnels. Subways. Industrial transport). Engineering and geodetic surveys are in force. Reference book of base prices for engineering and geodetic surveys during the construction and operation of buildings and structures. Geotechnical surveys are in force. Reference book of base prices for engineering-geological and engineering-environmental surveys for construction hydrographic works Directory of basic prices for engineering surveys for construction Engineering and hydrographic works Engineering and hydrometeorological surveys on rivers (Entered into force on 01.01.2001 instead of: chapters 3 (tables 62, 63); 5 (tables 86, 87, 90-92); 6; 7; 8 (Table. Coefficients on salary benefits are in effect Recommendations for determining the coefficient to the base prices for design work, taking into account the additional costs of organizations for preferential salary payments. for engineering and geodetic surveys for construction. a book of basic prices for measuring work and surveys of buildings and structures. The survey of building structures is in force. Reference book of base prices for design work on the survey, assessment of the technical condition, testing and strengthening of building structures of buildings, structures, cranes and hoists. 2nd edition. Water supply and sewerage facilities are in operation. Allowance A practical guide to the application of the reference book of base prices for design work for construction. Water supply and sewerage facilities. Operating Water supply and sewerage facilities Reference book of base prices for design work for construction. Water supply and sewerage facilities. The objects of the gas industry are in operation. Manual A manual for determining the relative cost of developing project documentation. Gas industry facilities (2nd edition). The objects of the gas industry are in operation. Practical guide A practical guide for the use of the reference book of base prices for design work for construction. Gas industry facilities (2nd edition). Operates Gas industry facilities Reference book of base prices for design work for construction. Gas industry facilities (2nd edition). Operates Civil aviation facilities Reference book of base prices for design work for construction. Civil aviation facilities. The objects of housing and civil construction are in operation. Manual A manual for determining the relative cost of the development of design and estimate documentation. Objects of housing and civil construction. The objects of housing and civil construction are in operation. Practice. allowance A practical manual for the use of the reference book of base prices for design work for construction. Objects of housing and civil construction. Operates Objects of housing and civil construction Reference book of base prices for design work for construction. Objects of housing and civil construction. Forestry facilities are in operation. Allowance A practical guide to the application of the reference book of base prices for design work for construction. Forestry facilities. Active Forestry facilities Reference book of base prices for design work for construction. Forestry facilities. The objects of the main oil transportation are in operation. Allowance A practical guide to the application of the reference book of base prices for design work for construction. Main oil transportation facilities. Operating facilities Main oil transportation facilities Reference book of base prices for design work for construction. Main oil transportation facilities. Facilities of the machine-building industry are in operation. Allowance A practical guide to the application of the reference book of base prices for design work for construction. Engineering industry facilities. Operating Facilities of the machine-building industry Reference book of base prices for design work for construction. Engineering industry facilities. The objects of the oil industry are in operation. Allowance A practical guide to the application of the reference book of base prices for design work for construction. Oil industry facilities. Operating Objects of the oil industry. Reference book of base prices for design work for construction. Oil industry facilities. Facilities of the building materials industry are in operation. Allowance A practical guide to the use of the reference book of base prices for design work for construction. Building materials industry facilities. Operating Facilities of the building materials industry Reference book of base prices for design work for construction. Building materials industry facilities. River transport facilities are in operation. Handbook A practical guide for the use of a reference book of base prices for design work for the construction of river transport facilities. Operates River transport facilities Reference book of base prices for design work for construction. River transport facilities. Communication objects are in effect. Manual 1. A manual for determining the relative cost of developing project documentation for communication facilities. Communication objects are in effect. Allowance 2. A practical guide to the application of the Reference book of base prices for design work for construction "Communication facilities" (General provisions). Communication objects are in effect. Allowance 3. Practical guide on the use of the Reference book of base prices for design work for construction "Communication facilities" (Explanations on the procedure for applying the base prices for design work for the construction of electrical and postal communication facilities - tables 1-10, 22. for design work for construction. Communication facilities. Operations Pulp and paper industry. Manual A practical guide for the use of a reference guide for design work for the construction of the pulp and paper industry. Operational Facilities for the pulp and paper industry Reference book of base prices for design work for construction. Objects of the pulp and paper industry. Manual of reference prices for design work for construction. Energy facilities. A guide for determining the relative cost of developing project documentation and the unit cost of developing working documentation for buildings, structures and types of work. Energy facilities are in operation. Practical guide A practical guide for the use of the reference book of base prices for design work for construction. Energy facilities. (basic provisions). Operating Energy facilities Reference book of base prices for design work for construction. Energy facilities. Operating enterprises of transport, storage of petroleum products and gas stations Reference book of base prices for design work for construction. Enterprises of transport, storage of petroleum products and gas stations. The company operates a transport, storage of petroleum products. Allowance A practical guide to the use of the reference book of base prices for design work for construction. Enterprises of transport, storage of petroleum products and gas stations. The development of documentation for the process control system is in force. Reference book of base prices for the development of technical documentation for automated control systems for technological processes (APCS). Development of design documentation is in effect. Manual A practical manual for the use of a reference price guide for the development of design documentation for custom-made equipment. Working Development of design documentation Reference book of base prices for the development of design documentation for custom-made equipment. Working Development of technical documentation for overhaul Reference book of base prices for the development of technical documentation for overhaul of building structures of buildings and structures. Clarifications on the application are in force Clarifications on the use of the collection of prices and reference books of basic prices for design work for construction. Fire and security systems are in operation. Allowance A practical guide to the application of the reference book of base prices for design work for construction. Fire and security protection systems. Fire and security protection systems are in operation. Reference book of base prices for design work for construction. Fire and security protection systems. Active
1. General Provisions
2. The procedure for determining the base price of design work, depending on the natural indicators of design objects
Chapter 2.1. Residential buildings, hotels, hostels (to tables No. 1, 2)
Chapter 2.2. Health care and recreation facilities (to tables No. 3, 4)
Chapter 2.3. Physical culture and sports facilities (to tables No. 5 - 11)
Chapter 2.4. Objects of education and preschool institutions (to tables No. 12 - 13)
Chapter 2.5. Objects of culture and art (to tables No. 14 - 21)
Chapter 2.6. Research institutions, design and engineering organizations (to table No. 22)
Chapter 2.7. Buildings of trade and public catering enterprises (to tables No. 23 - 24)
Chapter 2.8. Administrative buildings (to table No. 25)
Chapter 2.9. Objects of consumer services for the population (to table No. 26)
Chapter 2.10. Public utilities facilities (to tables No. 27 - 32)
Chapter 2.11. Urban electric transport (to tables No. 33 - 38)
Chapter 2.12. Models of residential and civil buildings and structures (to table No. 39)
3. The procedure for determining the base price of design work, depending on the total cost of construction
4. Base prices for the development of design and working documentation
Table 1. Residential buildings
Table 2. Hotels, boarding houses, hostels
Table 3. Health care facilities
Table 4. Recreational facilities
Table 5. Specialized buildings for physical culture and sports
Table 5a
Table 6. Facilities for swimming and diving
Table 6a
Table 7. Shooting ranges
Table 7a
Table 8. Facilities for winter sports
Table 8a
Table 9. Tribunes
Table 10. Plane structures
Table 11. Auxiliary sports buildings and facilities
Table 12. Buildings of preschool institutions, educational institutions
Table 13. Educational-laboratory and educational buildings of technical, polytechnic, agricultural, medical, humanitarian and other higher educational institutions. Technical schools. Colleges ……………
Table 14. Cultural and educational buildings
Table 15. Theater and entertainment enterprises
Table 16. Film studios
Table 17. Factory of mass printing of motion pictures
Table 18. Filmmaking at telecentres
Table 19. Separate buildings, workshops of film studios
Table 20. Film rental companies
Table 21. Film storages
Table 22. Research institutions, design and engineering organizations
Table 23. Buildings of trade enterprises
Table 24. Buildings of public catering establishments
Table 25. Administrative buildings
Table 26. Objects of consumer services for the population
Table 27. Communal laundries and baths
Table 28. Ornamental nurseries. Flower greenhouses. Gorzelenstroy bases
Table 29. Crematoria, civil funeral ritual buildings, salons and specialized service bureaus, cemeteries
Table 30. Plants for the processing of solid household waste, landfill for burial of solid household waste, stations for sorting, reloading solid household waste
Table 31. Operating bases of gas facilities
Table 32. Engineering preparation of the territory, embankments
Table 33. Tram, trolleybus depot, track workshops, electrical workshops
Table 34 Terminal stations on tram (trolleybus) routes
Table 35 Ground light rail lines. Ordinary tram lines
Table 36 Contact networks and transport hubs of trolleybus and tram lines
Table 37 Traction substations
Table 38 Electrical calculation of tram and trolleybus networks
Table 39. Layouts of residential and civil buildings and structures with a display of interiors and equipment
Table 40 Base prices for design work for the construction of unique buildings and structures
Table 41. Recommended approximate relative cost of development of sections of project documentation (as a percentage of the base price) ... .................. ...
Table 42: Recommended Estimated Relative Cost of Working Paper Development (Percentage of Base Price)

1.1. The state estimate standard "Reference book of base prices for design work for construction" Objects of housing and civil construction "(hereinafter referred to as the Directory) is intended to determine the cost of developing design and working documentation for the construction of civil housing objects.

1.2. When using this Guide, one should be guided by the Guidelines for the use of reference books of base prices for design work for construction, approved by order of the Ministry of Regional Development of the Russian Federation of December 29, 2009 N 620 (hereinafter - Guidelines).

1.3. The level of prices contained in the tables of the Reference is established as of 01.01.2001.

1.4. Base prices in the Directory are set depending on the natural indicators of the projected objects: area, volume and others (hereinafter referred to as the main indicators of objects). For unique objects of housing and civil construction, base prices are given depending on the total cost of construction.

1.5. The distribution of the base price for the development of design and working documentation, determined according to the tables of the Reference Book, is carried out according to the ratio below and can be clarified by agreement between the contractor and the customer.

Types of documentation:

Percentage of base price:

Project documentation

Working documentation

Total

1.6. In the event that, as part of the project documentation, on behalf of the customer, works on the assessment of the environmental impact of the capital construction facility (EIA) are performed, the price is determined at 4% of the total design cost.

2. The procedure for determining the base price of design work, depending on the natural indicators of design objects

2.1. The basic prices of this section of the Handbook do not take into account the design:

· industrial building products;

· drainage;

· reclamation of disturbed lands;

· off-site networks, structures (district transformer substations, boiler houses, central heating points, treatment, water intake facilities), booster water pumping stations, sewage pumping stations;

· transfer of engineering networks within the construction site and removal of engineering networks from the construction site, as well as shifted engineering networks and structures outside the designated area.

2.2. The basic prices of the Guide take into account the costs of designing engineering networks and structures within the construction site, except for cases specifically stipulated by the relevant paragraphs of this Guide.

2.3. The base price for designing a construction object in difficult (cramped) environmental conditions (an object in a historical environment, in a protected landscape zone) is determined by agreement with the customer using a pricing coefficient of up to 1.1 to the cost of developing project documentation.

2.4. The base price for the design of combined or interlocked buildings and structures, as well as buildings with built-in premises for other purposes, if this combination, blocking or incorporation is not provided for by the norms for their design, is determined by summing up the prices for the design of the combined or blocked individual buildings and structures, as well as the main buildings and built-in premises.

In this case, the base price for the design of the main building is taken with a coefficient of 1, the cost of buildings or built-in premises blocked with it is taken with a decreasing coefficient as agreed with the customer, but not more than 0.8 and 0.5, respectively.

Chapter 2.1. Residential buildings, hotels, hostels (to tables N 1, 2)

2.1.1. Basic prices do not include the cost of designing boiler houses, transformer substations.

2.1.2. The base design price using design documentation for repeated or mass use ("binding") is determined with the introduction of the following pricing factors into the calculation:

· without making changes to the overground part of buildings - from 0.1 to 0.25;

· with changes to the overground part of buildings, changes in facades and layouts, including changes in number of storeys, roof structures - up to 0.7;

2.1.3. In the case of performing work on objects of repeated or mass use on the basis of the block-sectional method, the base price of design work on the development of a basic block-section is determined with a pricing coefficient of 0.8. In this case, the base price of work on the layout of the house is determined with a coefficient of up to 0.2.

2.1.4. The cost of block sections developed on the basis of a basic block section as part of a single series is determined with a pricing factor of up to 0.7 of the cost of a basic block section, depending on the complexity of their design.

2.1.5. When designing objects consisting of multiple (more than three times) repeating sections or buildings, the base price is set using correction factors to the cost of work on the repeating sections (buildings) in accordance with clause 2.1.2. In this case, the cost of developing the base section (building) is determined in the same way as calculating the cost for a separate building.

2.1.6. When determining the base price for the design of objects according to this Handbook, the following features must be taken into account:

· the cost of developing standard projects of block - sections with end facades and a wheelchair is determined at the prices of residential buildings;

· the volume of the building is determined without taking into account the volumes of the technical floor, attic and underground.

2.1.7. When determining the base price for the design of objects according to this Guide, the following features must be taken into account:

· the basic design price of hotels of the four-star and five-star categories is determined by the price indicators of points 4-6 of the table with pricing coefficients, respectively, 1.2 and 1.3;

· the base price for the design of hotels with attached restaurants is determined in accordance with clause 2.4 of this Guide;

· the base price of designing boarding houses with medical functions for the disabled is determined at the prices of items 1-3 of this table using a pricing coefficient of 1.15.

Chapter 2.2. Health care and recreation facilities (to tables N 3, 4)

2.2.1. This chapter contains basic prices for determining the cost of developing design and working documentation for new construction of complexes and individual buildings and structures of healthcare and recreation facilities.

2.2.2. A complex of a medical institution means a number of functionally interconnected buildings and structures located on the same territory and having common communications, a single system of energy supply, water supply, and the like.

The complex includes: the main building of the hospital (maternity hospital), a polyclinic (women's consultation), combined with a hospital, medical, medical and diagnostic buildings, as well as utility and auxiliary buildings and structures.

The complex does not include: centralized auxiliary and production and economic services (pathological buildings, garages, warehouses, workshops, etc.), as well as separate auditoriums, conference rooms, medical schools with dormitories serving several medical institutions of various profiles.

2.2.3. When determining the base price for the design of objects according to tables N of this Handbook, the following features must be taken into account:

· the total area of ​​buildings or structures listed in paragraphs 1-8 of tables N and is determined as the sum of the areas of all floors (including technical, attic, basement, basement); without sheds, small forms of architecture, households, garage;

· the base price for designing holiday homes "four stars" and "five stars" is determined at the prices of points 3, 4 using a pricing coefficient of up to 1.2;

· the base price for designing a rehabilitation center for the disabled is determined at the prices of items 5, 6 using a pricing coefficient of up to 1.15;

· the prices of the tables do not take into account the design of beaches with structures on them, dredging, bank protection works, piers and slipways;

· the base design price outside the complex of dormitories for tourist centers and camps is determined at the prices of points 3, 4 using a pricing coefficient of up to 0.7;

· the base price for the design of buildings and complexes for summer operation is determined using a pricing coefficient of up to 0.5.

Chapter 2.3. Physical culture and sports facilities (to tables N 5-11)

2.3.1. This chapter contains the base prices for the development of design and working documentation for the construction of sports and physical culture and recreation facilities for mass use.

2.3.2. The basic prices for flat and special structures take into account the cost of designing only the main structures without service and auxiliary structures and premises within the boundaries of the structure (sites, fields, and so on).

2.3.3. The base prices for sports buildings and swimming pools take into account the design of the main elements (halls, baths) and mandatory auxiliary premises.

The price includes design work within the boundaries of the development, determined by the territory within a fifteen-meter zone from the building outline, including the inputs of engineering communications.

2.3.4. The base price for the design of the complexes is determined by summing up the prices for the development of design and working documentation for sports facilities that are part of it; in the case of placing various structures of the complex in a single volume or interlocked, the cost of design work is determined using a pricing coefficient of up to 1.2.

2.3.5. The base design price for gyms and swimming pool baths built into residential and public buildings is determined based on the prices of the respective facilities (Table N of this Handbook) using a pricing coefficient of up to 0.5.

2.3.6. The base price for designing sports buildings and swimming pools with stationary seats for spectators with the number of spectators in buildings up to 500 people and pools up to 1000 people (excluding seats on balconies) is determined at the prices of the corresponding structures (Table N, of this Handbook) using the pricing coefficient up to 1.2.

2.3.7. When designing complexes at the request of the customer, the price of which is formed by summing the prices for physical culture and sports facilities of this Handbook, the base price of the master plan, vertical planning, landscaping, landscaping and on-site utilities is determined by applying the following pricing coefficients to the price of the complex, depending on the area of ​​the allotted site and the degree of development with volumetric structures:

· territory from 0.5 to 3 hectares, building area up to 30% - 0.25;

· territory from 0.5 to 3 hectares, building area over 30% - 0.2;

· territory from 3 to 10 hectares, building area up to 30% - 0.2;

· territory from 3 to 10 hectares, building area over 30% - 0.15;

· territory over 10 hectares, building area up to 30% - 0.15;

· territory over 10 hectares, building area over 30% - 0.1.

2.3.8. The cost of implementation of a construction organization project, determined during the development of project documentation for the construction of complexes, is 5%.

2.3.9. Basic prices do not take into account the design of engineering structures (heating station, refrigeration station, transformer substation, water booster pumping station, and so on) that ensure the operation of the projected structures or a complex of structures.

2.3.10. In the design of air-conditioned sports facilities, a 1.15 pricing factor is applied to the base prices.

2.3.11. Basic prices excluded:

· amplification and simultaneous translation of speech;

· production of booklets;

· ski slopes, fitness clubs, bowling alleys;

· calculations of natural illumination of objects located close to the projected objects in the existing urban development.

2.3.12. The base price for designing open skating rinks with artificial ice is determined at the corresponding price of paragraph 4 of this Handbook using a pricing coefficient of up to 0.7.

2.3.13. The base price for the design of outdoor pools is determined at the corresponding prices in this Handbook using a pricing factor of up to 0.8;

2.3.14. * When determining the base price for designing objects according to this Handbook, it is necessary to take into account that the base price for designing stands when additional under-stands premises are included is determined using the coefficients of Table 9a of this Handbook.

2.3.15. ** The base cost of designing objects according to tables N - of this Handbook, when additional premises are included in their composition, is determined using the coefficients given in the corresponding tables N-9a of this Handbook.

2.3.16. The base price for designing springboards according to this Handbook with scaffolds and coaching stands is determined using a pricing factor of up to 1.2.

_____________________

* Clause 2.3.14 should read: “When determining the base price for the design of objects according to No. 9 of this Handbook, it is necessary to take into account that the base price for the design of stands with the inclusion of additional under-stands premises is determined using the coefficients of Table No. 8a of this Handbook. "

** Clause 2.3.15 should read: "Basic the cost of designing objects according to tables N - of this Handbook when additional premises are included in their compositionis determined using the coefficients given in the corresponding tables N - of this Handbook ".

Chapter 2.4. Objects of education and preschool institutions (to tables N 12-13)

2.4.1. When determining the base design price according to this Guide, the total area of ​​preschool institutions and educational institutions does not include the area of ​​sheds, small forms of architecture, cold verandas, hozsarai, garage.

2.4.2. When determining the base price for the design of objects according to this Guide, the following features must be taken into account:

· the base design price for buildings of 10 floors and above is determined from the table prices using a pricing factor of 1.15;

· the base price for designing a computer center, student canteens, dormitories, assembly halls, libraries, sports and health camps is determined additionally.

Chapter 2.5. Objects of culture and art (to tables N 14-21)

2.5.1. When designing objects of culture and art with an expanded (reduced) composition of premises, maximum saturation with technological equipment (the required minimum of equipment that ensures the technological process), provided for by regulatory documents, base prices are adopted with application to sections of design and working documentation, the labor intensity of which varies depending on from the listed factors, the coefficient from 0.8 to 1.2 as agreed with the customer.

2.5.2. When determining, according to this Guide, the base price for designing cinemas that combine stage and spectator complexes of two or more halls, as well as foyers used as stage areas, is determined by summing the prices of two or more cinemas. In this case, the following coefficients are applied to the price of the second and subsequent cinemas:

· 0.8 - to the technological section of the project documentation;

· 0.5 - to the architectural, construction and engineering sections of the project documentation.

2.5.3. The basic prices of theater and entertainment enterprises (this Guide) provide for the design of single-hall theaters, cinema and concert halls and circuses, the capacity intervals of which are stipulated by regulatory documents, equipped with an optimal composition of technological equipment located in year-round buildings with a normal composition of premises that have a sufficient level of comfort.

2.5.4. The basic prices of this Handbook do not take into account the design of:

· soundproofing for people with partial hearing loss;

· broadcasts and notifications in 2 or more directions;

· speech translation and conference systems;

· large screen television installations;

· outside radio and television broadcasting;

· laser installations;

2.5.5. The base prices of this Handbook are set for the design of theaters and cinema and concert halls with standard sizes of stages and stages provided for by regulatory documents. When designing scenes and stages of other types, the cost of developing sections and types of design work in terms of the stage complex is determined with coefficients that take into account the listed factors:

· panoramic, three-sided, central, with a backstage, designed in addition to the grate stage - up to 1.3;

· panoramic, three-sided, central, with a backstage, projected instead of the grate stage - up to 0.7.

2.5.6. The base price for the design of technological systems for scenes with curved outlines in plan, in longitudinal or cross sections is determined according to this Handbook with the application of the coefficient taking into account complicating factors to the relevant sections - up to 1.2 as agreed with the customer.

2.5.7. When designing theaters for two or more troupes on one hospital with a common main hall, the base price is determined according to this Guide with a pricing factor of up to 1.15 as agreed with the customer.

2.5.8. The base price for designing a theater auditorium as a citywide universal hall intended for holding the most significant public events, in accordance with the design assignment, which provides for additional requirements for the composition of areas and equipment of premises, is determined at the corresponding prices of this Guide with a pricing factor of up to 1.2 as agreed with the customer.

2.5.9. The basic prices of objects of cinematography in tables N - of this Handbook do not take into account the design of:

· thermal treatment plants for industrial wastewater;

· dewatering;

· special treatment facilities for technological effluents.

Chapter 2.6. Research institutions, design and engineering organizations (to table N 22)

2.6.1. The price for the design of the complex of the research institute in this Handbook takes into account the design of the following buildings: laboratory and research, administrative, warehouse, experimental workshops and power plants.

2.6.2. The base price for the design of observatories, astronomical structures, buildings of research institutes dealing with the problems of nuclear physics, space exploration, particle accelerators, class I and II radioactive isotopes of ultra-high-voltage technology, super-powerful electrical equipment, special converting devices, especially dangerous infections, genetic engineering with a degree protection F3 and F4, new directions in the field of electronics and cybernetics is determined in relation to the prices of the table with a pricing factor of 1.8.

2.6.3. When designing research institutes located in areas of existing development, in cities with a population of more than 250 thousand people. a pricing coefficient of up to 1.1 is applied to prices, in cities with a population of 1 million people. and higher - up to 1.2.

2.6.4. The base design price for buildings of 10 floors and above is determined according to this Handbook using a pricing factor of 1.15.

2.6.5. The basic design price of research institutions for humanitarian purposes is determined at the prices of items 1, 2 of this Handbook using a pricing factor of 0.7.

2.6.6. The base price for the design of the complex of buildings of the pilot production takes into account the design of the compressor room and the central heating station.

2.6.7. The prices of this Handbook do not include the design of:

· overpasses and through collectors;

· industrial television and speech translation installations;

· Automatic telephone exchange;

· compressor room, cryogenic, hydrogen, nitrogen, oxygen stations and the like;

· chemical protection of structures and pipelines;

· special water treatment stations (distilled, deionized, etc.);

· stations for special cleaning of process gases.

2.6.8. The prices of paragraphs 15, 16 of this Handbook do not take into account the design of the technical library.

Chapter 2.7. Buildings of trade and public catering establishments (for tables N 23-24)

2.7.1. The basic design cost of lightweight buildings is determined based on the prices of tables N of this Handbook using a pricing factor of up to 0.7.

Chapter 2.8. Administrative buildings (to table N 25)

2.8.1. When determining the base price for the design of objects according to this Guide, the following features must be taken into account:

· the base price of designing judicial institutions is determined at the prices of points 1.2 * with a pricing coefficient of up to 1.15;

· when designing buildings listed in clauses 1-6 with air conditioning, a pricing factor of up to 1.2 is applied to the cost of the relevant sections.

________________________

Chapter 2.9. Objects of consumer services for the population (to table N 26)

2.9.1. This Handbook provides basic prices for the development of design and working documentation:

· dry cleaning enterprises;

· enterprises for washing linen and dry cleaning of clothes;

· household electronic equipment repair enterprises;

· enterprises for the repair of household machines and appliances;

· shoe repair and sewing enterprises;

· enterprises of repair and tailoring of clothes;

· enterprises for the repair and manufacture of knitwear;

· furniture manufacturing and repair enterprises;

· enterprises for photographic cinematography;

· rental studio;

· pawnshops;

· complex reception centers, including hairdressing and other types of personal services.

2.9.2. The basic prices of this Guide do not include the cost of designing industrial television, boiler room.

Chapter 2.10. Public utilities (to tables N 27-32)

2.10.1. The prices of this chapter do not include: certification and inventory of land plots, buildings, structures; small architectural forms, boiler houses (except for items 1-4 of this Handbook), construction dewatering, transfer and removal from the construction zone of ground and underground communications, roads

2.10.4. When determining the base price for the design of objects according to this Guide, the following features must be taken into account:

· the prices of points 1 and 2 do not take into account the cost of designing water treatment facilities;

· the base price for designing a hygienic bath, interlocked with an urgent laundry, is determined at the prices of points 3 and 4 using a pricing factor of up to 1.3;

· When designing a water softener, a pricing factor of 1.02 is applied to the table prices.

2.10.5. When determining the base price for the design of objects according to this Guide, the following features must be taken into account:

· the base price for designing embankments with a curvilinear outline in the plan is determined using a pricing coefficient of up to 1.15;

· the base price for designing slope embankments is determined using a pricing coefficient of up to 0.4;

· the base price for the design of vertical embankments is determined using a pricing coefficient of up to 0.8;

· basic prices take into account the design of bank strengthening, ramps, descents, embankment junctions at its beginning and end, gutters and construction dewatering;

· the base price for designing the intersection of the embankment with existing and projected communications and structures is determined additionally.

Chapter 2.11. Urban electric transport (to tables N 33-38)

2.11.1. The prices of this chapter do not take into account the costs of: design of water supply and culverts and trays; development of measures for the safety of existing facilities falling into the construction zone; development of a project for the organization of a sanitary protection zone; development of a dendroplan and drawing up a statement with the calculation of the compensation cost for the demolished green spaces.

2.11.2. The base prices of this chapter provide for the design according to geodetic plans on a scale of 1: 500. When designing according to geodetic plans at a scale of 1: 200, a pricing factor of 1.15 is applied to prices.

2.11.3. When crossing metro lines and structures, a coefficient of up to 1.2 is applied to the design prices of urban electric transport facilities located in their zone.

2.11.4. When designing objects in cities with a population of 500 thousand people to 1 million people, a pricing coefficient of up to 1.1 is applied to prices, a coefficient of up to 1.2 for a population of more than 1 million people, and a coefficient of up to 1 for the cities of Moscow and St. Petersburg. 4.

2.11.5. When determining the base price for the design of objects according to this Guide, the following features must be taken into account:

· if the length of tracks in the city is over 100 km, a pricing coefficient of up to 1.1 for every 25 km of track is applied to the prices in clause 10;

· for electrical workshops, the main indicators of which differ from those given in the table, the design price should be determined by extrapolation by the sum of the main indicators of power and length.

2.11.6. The base prices of this Handbook do not include:

· distribution substations of power systems;

· anti-landslide measures;

· traction substations.

2.11.7. When determining the base price for the design of objects according to this Guide, the following features must be taken into account:

· base prices are for the design of terminal stations outside the complex;

2.11.8. When determining the base price for the design of objects according to this Guide, the following features must be taken into account:

· as a unit of measurement of the length of the lines, their length in single-track calculation is taken. In this case, a reduction factor of up to 0.3 is applied to the design cost of the adjacent second track.

· basic prices are given for lines with two end reversal rings with the length of the curves in the plan no more than 15% of the length of the projected lines. The cost of additional, in excess of 15%, curved line sections and additional turning rings is determined with a coefficient of 1.15 for each kilometer of curves.

2.11.9. The base prices of this Handbook do not include:

· removal from the construction zone and reconstruction of roads and railways, tram and trolleybus lines;

· structures: tram depot, terminal stations, workshops for electrical and track facilities, central control points;

· bridges, overpasses, overpasses and pipes with a diameter of more than 1.5 m;

· city ​​streets, roads and underground drains;

· power supply of 6 (10) kV alternating current and 0.6 kV direct current, electrical calculations of traction networks, calculations of the influence of power lines and electrified railways;

· telemechanization of traction substations;

· notification at stopping points;

· motorways along the highway;

· Specialists of contact networks in artificial structures.

2.11.10. In the case of joint design of surface light rail lines or conventional tram lines with city streets, a pricing factor of 0.9 is applied to the prices of this Guide.

2.11.11. When determining the base design cost according to this Handbook, the following features must be taken into account:

· base prices are given for lines - in one direction of movement. At the same time, a reduction factor of up to 0.3 is applied to the cost of designing a nearby second line.

· basic design prices for transport hubs are given - depending on the number of special parts;

· the base price for designing a trolleybus contact network is determined by separate lines, the length of which is limited by turning rings, turning rings or transport hubs;

· the base price for designing a tram line overhead line is determined according to items 1, 2 using a pricing coefficient of up to 0.9;

· the base price for designing the air network of automatic tram switches is determined according to items 1, 2 using the price-forming coefficient 0.9;

· the base price for designing an overhead power supply network for the contact network of tram and trolleybus lines is determined in paragraphs 1, 2 using a pricing factor of up to 0.8.

2.11.12. The base prices of this Handbook do not include:

· the construction of fastening insulating panels under artificial structures (overpasses, overpasses, pipelines, etc.);

· lighting and traffic light signaling of trolleybus lines;

· automatic switches at the nodes of the tram line, taking into account the cable and air network;

2.11.13. The basic prices of this Handbook do not take into account the design of control rooms and telemechanics points.

2.11.14. When determining the base price for the design of objects according to this Guide, the following features must be taken into account:

· this table shows the prices for performing electrical calculations of 0.6 kV DC traction networks for trolleybus lines, ordinary tram lines, local electrical calculations performed on a separate order;

· prices are given for the total length of tram (trolleybus) networks by settlement options and development queues, in single-track terms (one direction of travel).

Chapter N 2.12. Layouts of residential and civil buildings and structures (to table N 39)

2.12.2. The prices of this Handbook provide for the production of models and layouts with a display of buildings and structures, terrain relief, landscaping, small forms, roads, driveways, footpaths, sports grounds and other objects.

2.12.3. Measurement of the expanded area of ​​the facades is carried out:

· with flat roofs - to the top of the eaves of the building;

· with volumetric roofs - up to the ridge of the roof (top point of the roof).

2.12.4. The prices of this Guide are given for models made of wood, plastic, metal and other materials. The production of layouts from soft material (cardboard, foam, plasticine, gypsum, paper, and others) is determined using a pricing factor of 0.6.

2.12.5. The production of models for exhibitions and museums is determined using a pricing factor of 1.2.

2.12.6. The prices of this Guide provide for the production of models on a scale of 1: 100. When making layouts on other scales, pricing factors are applied to prices:

· at a scale of 1:20 - 0.6;

· at a scale of 1:50 - 0.8;

· at a scale of 1: 200 - 1.2;

· at a scale of 1: 500 - 1.4.

2.12.7. Making models without showing interiors and equipment is determined using a pricing factor of up to 0.5.

2.12.8. The production of collapsible models is determined using a pricing factor of up to 1.2.

2.12.9. When several detached buildings are placed on one stretcher, the price of making a layout is determined as the sum of the production of layouts of these buildings, while the production of layouts of accompanying buildings (all except the main one) is determined using a pricing coefficient of 0.9.

3. The procedure for determining the base price of design work, depending on the total cost of construction

3.1. The base price for the development of design and working documentation is set as a percentage of the total cost of construction of unique buildings and structures (this Guide).

3.2. The base price takes into account the cost of design work, which is reflected in the total cost of construction, corresponding to the final indicator of the cost of construction for chapters 1-12 of the Consolidated Estimated Construction Cost (SSRCC), with the exception of the cost of work listed in clause 1.3.6 of the Methodological Guidelines.

3.3. The cost of construction for determining the base price of design work is determined by an analogue object, taking into account their comparability or by aggregated indicators of the cost of construction (types of work).

4. Base prices for the development of design and working documentation

Table N 1... Dwelling houses

N p / p

but

in

Low-rise residential buildings

One-story

m 3

119,24

0,021

Two-story

183,72

0,019

Three-storey

273,44

0,017

Residential multi-apartment buildings:

Four-story

405,842

0,012

Five-story

553,133

0,012

Six - ten stories

902,246

0,012

Eleven thirteen-story

1008,586

0,015

Fourteen sixteen story

1278,490

0,045

Seventeen - twenty-story residential buildings

1662,038

0,118

Residential buildings over 20 floors

2045,578

0,145

Table N 2... Hotels, boarding houses, hostels

N p / p

Design object name

Unit of measurement of the main indicator of the object

Constant values ​​of the base price for the development of design and working documentation, thousand rubles

but

in

Youth hotels, boarding houses by number of places:

up to 100

a place

540,078

4,842

over 100 up to 500

636,178

3,881

over 500

710,178

3,733

up to 100

646,283

5,840

over 100 up to 500

760,883

4,694

over 500

849,883

4,516

Motels, hostels by number of places:

up to 100

a place

430,866

3,881

but

in

Complexes

Complexes of hospitals, maternity hospitals, dispensaries, medical centers with a total area, m 2

from 3500 to 8000

m 2

1148,71

0,20

over 8000 up to 70,000

1708,71

0,13

Separate buildings and structures designed outside the complex.

Medical, diagnostic, medical and diagnostic buildings; polyclinics, mud baths, outpatient clinics, first-aid posts, antenatal clinics, feldsher-obstetric points with a total area, m 2

up to 450

m 2

89,76

0,41

over 450 up to 900

107,76

0,37

over 900 up to 3300

134,76

0,34

over 3300 up to 20,000

464,76

0,24

Household buildings of hospitals, maternity hospitals, dispensaries (catering units, laundries), pathological and anatomical buildings, pharmacies, ambulance stations, sanitary and epidemiological stations, blood transfusion stations; disinfection stations, other specialized stations, dairy kitchens with a building volume, m 3

but

in

Complexes

Sanatoriums, sanatorium-preventoriums, complexes, specialized sanatoriums, year-round children's institutions with a total area, m 2

up to 10,000

m 2

1052,89

0,37

over 10,000

2552,89

0,22

Holiday houses of the "three stars" category, recreation centers, boarding houses, tourist centers with a total area, m 2

up to 4000

626,23

0,34

over 4000

946,23

0,26

Sports and recreation facilities with a total area, m 2

up to 4000

m 2

505,80

0,34

over 4000

825,80

0,26

Separate buildings and structures designed outside the complex

Sleeping buildings for sanatoriums, rest homes with a total area, m 2

but

in

Sports building with a hall size, m:

24 ´ 12

sport-

242,97

30 ´ 15

frame

257,10

30 ´ 18

314,30

36 ´ 18

324,79

42 ´ 24

389,51

42 ´ 42

655,53

Indoor cycling track with a track length of 250 m:

cycle track

1212,37

Pavilion - dressing room, (when designing outside the complex), m 3

m 3

69,61

0,06

Sports Palace, universal sports hall, ice palace:

up to 3000 seats

1000 seats

4116,42

550,40

over 3000 to 5000 seats

4414,89

450,91

over 5000 to 10000 seats

5146,09